Blasting, Volume. 42, Issue 3, 116(2025)

Blasting Demolition of Prestressed Continuous Rigid-frame River-crossing Bridges in Complex Environments

WANG Wei1,2, JIA Yong-sheng1,3、*, LIU Chang-bang1, YUAN Fang3, WU Yue1, and NIE Sen-lin3
Author Affiliations
  • 1Wuhan Explosion & Blasting Co., Ltd., Wuhan 430056, China
  • 2College of Science, Wuhan University of Science and technology, Wuhan 430065, China
  • 3State Key Laboratory of Precision Blasting, Jianghan University, Wuhan 430056, China
  • show less

    Prestressed continuous rigid-frame bridges, a prevalent structural system in large-span bridge construction, present unique demolition challenges due to spatial constraints and adjacent infrastructure constraints during demolition. This study examined the controlled demolition of a river-crossing, prestressed, continuous, rigid-frame bridge using a blasting demolition practice. The demolition strategy incorporated mechanical crushing of mid-span deck and wing plates, complemented by strategically positioned blasting cuts at critical structural elements, including piers, mid-span box girder webs, top slabs, external prestressed steel cable anchor piers, and bridge-end box girder connections. The implementation of a sequential detonation order (mid-span box girders followed by external prestressed cable anchor piers, concluding with bridge-end connections and piers) resulted in controlled segmental collapse. Numerical simulation using LS-DYNA's dynamic finite element analysis validated the demolition scheme, revealing key process parameters: a total collapse duration of 4.5 seconds and a deck impact velocity of 13.6 m/s. The analysis identified impact stress as the primary mechanism for structural disintegration. A significant finding emerged regarding external prestressing technology. While originally implemented to enhance service performance and load-bearing capacity, the release of prestressing forces through controlled blasting was found to improve structural fragmentation efficiency significantly. Field implementation demonstrated the technical feasibility and safety of this approach, providing an effective solution for dismantling long-span, prestressed, continuous, rigid-frame bridges in complex environments. The study establishes a comprehensive framework for similar demolition projects, highlighting the importance of integrated mechanical and explosive techniques in modern bridge demolition engineering.

    Tools

    Get Citation

    Copy Citation Text

    WANG Wei, JIA Yong-sheng, LIU Chang-bang, YUAN Fang, WU Yue, NIE Sen-lin. Blasting Demolition of Prestressed Continuous Rigid-frame River-crossing Bridges in Complex Environments[J]. Blasting, 2025, 42(3): 116

    Download Citation

    EndNote(RIS)BibTexPlain Text
    Save article for my favorites
    Paper Information

    Category:

    Received: Feb. 13, 2025

    Accepted: Sep. 18, 2025

    Published Online: Sep. 18, 2025

    The Author Email: JIA Yong-sheng (422103951@qq.com)

    DOI:10.3963/j.issn.1001-487x.2025.03.013

    Topics